Construction Photos - Week of 05/09/08

  • Image
    Looking at the Contact Basin from the SW corner
  • Image
    Looking at the Clearwell walls from the SW corner of the Contact Basin
  • Image
    Looking at the Washwater Recovery Basin sloped slab excavation west of the BWR Pump Room
  • Image
    Looking at the south end of the Clearwell wall pour #2 from outside the structure at a slight cold joint approximately 4’ above the floor
  • Image
    Looking at the Clearwell wall SE corner (pour #4)
  • Image
    Looking at the NE corner of the Clearwell wall (pour #2)
  • Image
    Looking at the Contact Basin from the SW corner
  • Image
    Looking at the Clearwell south wall in the SE corner (pour #4)
  • Image
    Looking at the water stop and control joint in the east well of the Clearwell from the floor going up
  • Image
    Looking at the water stop and control joint in the east well of the Clearwell from the floor going up
  • Image
    Looking at the water stop and control joint in the east well of the Clearwell from the floor going up
  • Image
    Looking at the north Clearwell wall on the west end from inside (pour #5)
  • Image
    Looking at the north Clearwell wall on the west end from inside (pour #5)
  • Image
    Looking at the water stop at the control joint in the east Clearwell wall
  • Image
    Looking at the north wall of the Clearwell structure on the west end
  • Image
    Looking at the north wall of the Clearwell structure on the west end
  • Image
    Looking at Contact Basin from the SW corner
  • Image
    Looking at Clearwell walls from the SW corner of the Contact Basin
  • Image
    Looking at the shoring for the BWR Pump Room upper slab from the SE corner
  • Image
    Looking at the corrected water stop at the control joint in the east Clearwell wall
  • Image
    Looking at the SE corner wall of the Clearwell structure being placed (pour #4)
  • Image
    Looking at the concrete crew during the SE corner wall placement on the Clearwell
  • Image
    Looking at the Washwater Recovery Basin fill west of the BWR Pump Room
  • Image
    Looking at dewatering pump setup west of the Washwater Recovery Basin sump slab
  • Image
    Looking at the upper slab support decking for the BWR upper slab
  • Image
    Looking at the area east end of the site from on top of the 3:1 slope north of the BWR
  • Image
    Looking at the BWR Pump Room from on top of the 3:1 slope north of the BWR
  • Image
    Looking at the area between the Clearwell and Washwater structures from on top of the 3:1 slope north of the BWR
  • Image
    Looking at the Clearwell structure from on top of the 3:1 slope north of the BWR
  • Image
    Looking at the Clearwell structure from on top of the 3:1 slope north of the Clearwell
  • Image
    Looking at the west end of the site from on top of the 3:1 slope north of the Clearwell
  • Image
    Looking at the west end of the site from on top of the 3:1 slope north of the Clearwell
  • Image
    Looking at the west end of the site from on top of the 3:1 slope north of the Clearwell