Facing east at the wash water basin foundation slab rebar placement
Facing east at the wash water basin foundation slab rebar placement
Facing east at the wash water basin foundation slab rebar placement
Facing southeast at construction of 2 sediment ponds for concrete aggregate wash system
Facing north at installation of 2" water line to concrete batch plant
Facing north at installation of 2" water line to concrete batch plant
Facing northwest at clear well basin from southeast corner
Facing northwest at clear well basin from southeast corner
Facing north at wash water basin rebar placement and form work
Facing northwest at additional excavation on northeast corner of the wash water structure (see RFI #11)
Facing south at wash water basin form work and rebar placement
Fat clay yielding area south side of clear well contact basin subgrade
Fat clays yielding area south side clear well contact basin subgrade
Facing NW at clear well slab area NW corner